Final EIA Report completed

Wind Prower Plant Imret project is split into two parts for the environmental permitting purposes. Part 1, consisting of 23 confirmed and 6 reserve positions is attributed 85 MW and Part 2, consisting of 4 confirmed and 1 reserve positions is attributed 15 MW. Part 2 is adjacent to Surami Emerald site and the turbine […]

Read more

Public Awareness campaign in Korbouli

Infinite Energy LLC has started land acquisition procedures that are required for wind turbine installations and building the access roads. The certain part of the required land parcels are privately held and we decided to start off with meetings with affected population and explain and deliver the project concept in plain language before negotiating the […]

Read more

Public Awareness campaign in Khvani and Chalovani

Infinite Energy LLC has started land acquisition procedures that are required for wind turbine installations and building the access roads. The certain part of the required land parcels are privately held and we decided to start off with meetings with affected population and explain and deliver the project concept in plain language before negotiating the […]

Read more

First 84m met mast is up and collecting wind data

Today, we erected first met mast on site and started collecting the wind data. The met mast is 84 meters in height and accommodates First Class AMMONIT devices including 5 anemometers on 20, 40, 60, 80 and 84 meters heights respectively, two wind wanes for detecting the direction of the wind, Wildlife Acoustics sound decoder with […]

Read more